PROJECT

OUR PROJECT

Six laning & Strengthening of NH-248A from existing km 2.740 (Rajiv Chowk) to km 11.682 (Design Chainage 0+340 to 9+282) in Gurugram under NHDP Phase-IV on Hybrid Annuity Mode in the State of Haryana
Appointed Date 1-Feb-19
CONSTRUCTION PERIOD 910 Days
Scheduled Date of Completion 30-Jul-21
   
Utility Shifting Status  
Electrical  All estimates between KM 5+000 to end of project is approved by NHAI. Work is in Progress. LT line shifting estimates between 2+740 to 5+000 are pending at NHAI. 
PHE  All estimates are approved by NHAI, Work is in Progress. 
Removal of Encrachment All encroachment/Existing structures within ROW are removed by NHAI except six cases of court stay
Tree Cutting Work is in Progress
   
PRECONSTRUCTION ACTIVITY  
Camp & Establishment Set up  Completed 
Casting Yard including gantries  Completed 
Batching Plant Set up with all equipment  Completed 
   
Land Acquisition Status  
Total Land Required  51.07  Ha. 
Total Land Available   51.07  Ha. 
Additional Land Requirement 977  Sqm 
Likely availability of remaining land  31-Mar-20
   
Project works Status  
Elevated Structure(6 Lane)  
Foundation  266 Nos {out of 630} of 1.5m Dia pile and 38 Nos {Out of 119} Pile cap are completed 
Substructure  24 Nos {Out of 119} of Pier shaft and 2 Nos of Pier Cap are completed 
Superstructure  227 Nos {Out of 1770} of Spine segments & 44 Nos {Out of 3540} of Wing segments are completed 
Vehicular Overpass  
Guide/Diaphargm Wall  Guide wall construction is in progress for first phase, after errecting Barricading Board/ Traffic Diversion 
Foundation  Yet to start 
Superstructure  Yet to start 
Minor Bridges in MCW (6 Lane)  
Foundation  Yet to start 
Substructure  Yet to start 
Superstructure  Yet to start 
Minor Bridge for Service Road (3 Lane)  
Foundation  RHS Raft construction is complete. 
Substructure  RHS wall construction is in progress 
Superstructure  Yet to start 
BOX CULVERT  
Foundation  Complete for service road portion. MCW portion is in progress 
Substructure  Complete for service road portion. 
Superstructure  Complete for service road portion. 
Foot over Bridge  Yet to Start 
SERVICE ROAD  3800m {Out of 17884} complete as on date 
RCC DRAIN  3000m {Out of 17884} complete as on date 
MAIN CARRIAGEWAY  Will take up after diverting traffic on Service road and completing CD structures 
   
Total Physical Progress till 30th November, 2019 11.35% {Progress achieved till Oct'19 and Construction is banned in Nov'19 due to SC order}