| Appointed Date | 1-Feb-19 |
| CONSTRUCTION PERIOD | 910 Days |
| Scheduled Date of Completion | 30-Jul-21 |
| Utility Shifting Status | |
| Electrical | All estimates between KM 5+000 to end of project is approved by NHAI. Work is in Progress. LT line shifting estimates between 2+740 to 5+000 are pending at NHAI. |
| PHE | All estimates are approved by NHAI, Work is in Progress. |
| Removal of Encrachment | All encroachment/Existing structures within ROW are removed by NHAI except six cases of court stay |
| Tree Cutting | Work is in Progress |
| PRECONSTRUCTION ACTIVITY | |
| Camp & Establishment Set up | Completed |
| Casting Yard including gantries | Completed |
| Batching Plant Set up with all equipment | Completed |
| Land Acquisition Status | |
| Total Land Required | 51.07 Ha. |
| Total Land Available | 51.07 Ha. |
| Additional Land Requirement | 977 Sqm |
| Likely availability of remaining land | 31-Mar-20 |
| Project works Status | |
| Elevated Structure(6 Lane) | |
| Foundation | 266 Nos {out of 630} of 1.5m Dia pile and 38 Nos {Out of 119} Pile cap are completed |
| Substructure | 24 Nos {Out of 119} of Pier shaft and 2 Nos of Pier Cap are completed |
| Superstructure | 227 Nos {Out of 1770} of Spine segments & 44 Nos {Out of 3540} of Wing segments are completed |
| Vehicular Overpass | |
| Guide/Diaphargm Wall | Guide wall construction is in progress for first phase, after errecting Barricading Board/ Traffic Diversion |
| Foundation | Yet to start |
| Superstructure | Yet to start |
| Minor Bridges in MCW (6 Lane) | |
| Foundation | Yet to start |
| Substructure | Yet to start |
| Superstructure | Yet to start |
| Minor Bridge for Service Road (3 Lane) | |
| Foundation | RHS Raft construction is complete. |
| Substructure | RHS wall construction is in progress |
| Superstructure | Yet to start |
| BOX CULVERT | |
| Foundation | Complete for service road portion. MCW portion is in progress |
| Substructure | Complete for service road portion. |
| Superstructure | Complete for service road portion. |
| Foot over Bridge | Yet to Start |
| SERVICE ROAD | 3800m {Out of 17884} complete as on date |
| RCC DRAIN | 3000m {Out of 17884} complete as on date |
| MAIN CARRIAGEWAY | Will take up after diverting traffic on Service road and completing CD structures |
| Total Physical Progress till 30th November, 2019 | 11.35% {Progress achieved till Oct'19 and Construction is banned in Nov'19 due to SC order} |